Project description
The City will be carrying out redevelopment works on Montée des Tilleuls. The work will be carried out in collaboration with the following departments:
- VDL – Service Canalisation (Sewer Department): Refit of mixed wastewater drains due to disrepair. Replacement of deteriorated home connections. Correct installation of wrongly fitted connections to private buildings in the separate draining system.
- VDL – Service Eaux (Water Department): Replacement and upgrade of the water mains, and upgrade of private connections to bring them into compliance with existing requirements.
- VDL – Service Éclairage Public (Public Lighting Department): Replacement and upgrade of the public lighting system, and replacement of street lamps. Refit of public lighting cabinets to bring them up to code.
- VDL – Service Informatique (ICT Department – Fibre optics): Extension and upgrade of Luxembourg City's fibre-optic network and upgrade of its Wi-Fi network. Refit ITC cabinets to bring them up to code.
- VDL – Service Voirie (Department of Streets): The pavements will be made level with the street, in line with the criteria for a shared use areas. Change of drainage from two gullies along the sides of the street to a central gully. Complete rebuild of the superstructure with concrete pavers. Creation of two new footpaths to provide safe access to the bus stop on Rue de Rollingergrund. Replacement of an existing passage crossing the public thoroughfare in front of houses 2 and 2A.
- Creos-Électricité : Replacement and upgrade of the deteriorated and undersized low-voltage power network. Replacement of home power supply lines. Upgrade of public lighting connections and Creos electrical grids with VDL electric metre boxes.
- Creos-Gaz: Replacement of the deteriorated low pressure network. Replacement of the private connections with valves under the pavement and "Gas-STOP" safety valves at the connection with the principal gas main.
- POST Technologies: Extension of the ultra high-speed fibre-optic broadband network as part of the completion of the FTTH ("Fibre To The Home") project.
Works schedule
Commencement of works: autumn 2025
Expected duration of the works: 330 working days
Planned completion: spring 2027
Traffic information
For vehicular traffic
The affected sections will be gradually closed off to traffic as the project progresses.
Pedestrian access and access for emergency services will be guaranteed throughout the duration of the works. Vehicular access to private property will be maintained as long as physically possible.
For businesses and deliveries
The City of Luxembourg will try to ensure access for deliveries to local businesses throughout the duration of the works.
Changes to traffic flows will be implemented as the works progress. Appropriate signage will be put in place by the Service Circulation (Traffic Depatment). The City of Luxembourg thanks local residents, businesses and road users for their understanding and regrets any inconvenience that the works may cause.
Progress to date
How long will the work take?
Planned completion: 2027
What work remains to be done?
Commencement of preparation works: autumn 2027
Your home utility connections
- As part of the construction project, City representatives and private contractors will visit residents' homes.
- They will be assessing the condition of their existing connections.
- If you wish to have your existing connections replaced, please inform the City representatives during this on-site inspection.
If you experience a malfunction in your gas, water or communication system, please contact the 24-hour hotlines listed below.
- Service Eaux – Tel.: 4796-2883
- Creos Électricité – Tel.: 8002-9900
- Creos Gaz – Tel.: 8007-3001
- Post Luxembourg – Tel.: 8002-8004
- Eltrona – Tel.: 499 466 888
Stay informed
To make life easier for residents while these works are being carried out, the City of Luxembourg has implemented a series of measures, including the option to participate in meetings regarding the progress of the work. Residents affected by the works may participate in these meetings to obtain additional information about the project's progress and air any grievances they may have. Please contact the works coordinator or one of the construction mediators.
Weekly site meetings
The date will be published shortly.
Information session
An information session for local residents was held on 15 July 2025. A presentation of this development project is available below.
Contacts for this project
DEPARTMENT | CONTACT | PHONE NO. |
---|---|---|
VDL – Service Voirie | Martine Fey | 4796-2804 |
VDL – Construction Mediators | chantiers@vdl.lu | 4796-4343 |