Project description

Since March 2022, the City of Luxembourg has been carrying out redevelopment works on Montée du Grund and Rue Large. These works are being done in cooperation with:

  • VDL – Service Voirie (Department of Streets): Replacement of paving stones along the entire road surface. Separation of the roadway and the pavement through the installation of a gutter made up of a double row of paving stones. Creation of a pavement that is level to the roadway. Installation of a 2 m parking lane marked by a single row of paving stones.
  • VDL – Service Eaux (Water Department): Complete replacement of the principal water main and replacement of home utility connections that have deteriorated.
  • VDL – Service Éclairage public (Public Lighting Department): Replacement and upgrade of the public lighting system, and replacement of street lamps.
  • Creos Luxembourg SA Electricité: Replacement and extension of the deteriorated power network. Replacement of home utility connections.
  • Creos Luxembourg SA Gaz: Replacement of gas mains and private connections.
  • Post Luxembourg: Replacement of old cables with optical fibre and replacement of connections to houses.

Works schedule

Commencement of work: March 2022

Expected duration of the works: 340 working days

Planned completion: August 2023

Traffic information

What is the current traffic situation?

For vehicular traffic:

The sections being worked on will be closed off to traffic, one by one, as the project progresses. Montée du Grund and Rue Large are currently closed to all traffic except local residents and suppliers/deliveries. Pedestrian access and access for emergency services will be guaranteed throughout the duration of the works. Vehicular access to private property will be maintained as long as physically possible.

For businesses and deliveries:

The City of Luxembourg will try to ensure access for deliveries to local businesses throughout the duration of the works. As construction progresses, there will be changes to the flow of traffic in this area.

For public transport users:

No changes

Progress to date

How long will the work take?

Planned completion: August 2023

What work has already been completed?

The infrastructure and superstructure work on Rue Large and the pavement on Montée du Grund have been completed.

What remains to be done?

The infrastructure and superstructure work Montée du Grund remains to be completed.

Stay informed

To make life easier for residents while these works are being carried out, the City of Luxembourg has implemented a series of measures, including the option to participate in meetings regarding the progress of the work. Residents affected by the works may participate in these meetings to obtain additional information about the project's progress and present any complaints they may have.

Weekly site meetings

A meeting will be held on site every Wednesday at 10:15.

Information session

An information session for local residents was held on 20 January 2022. A presentation of this development project is available below.

Your home utility connections

  • As part of the construction project, City representatives and private contractors will visit residents' homes.
  • To assess the condition of their existing connections.
  • If you wish to have your existing connections replaced, please inform the City representatives during this on-site inspection.

If you have any problems with your gas, water or communications networks, please contact the services below, which are open 24/7:

  • Service Eaux – Tel.: 4796-2883
  • Creos Électricité – Tel.: 8002-9900
  • Creos Gaz – Tel.: 8007-3001
  • Post Luxembourg – Tel.: 8002-8004
  • Eltrona – Tel.: 499 466 888

Contacts for this work site

Department Contact Telephone number
VDL – Service Voirie Sébastian Schinner 4796-3879
VDL – Service Eaux Tom Wagener 4796- 4334
VDL – Service Éclairage public Daniel Perrard 4796-4989
VDL – Construction mediators chantiers@vdl.lu 4796-4343
Creos Électricité Claude Almeida 4796-5727
CREOS Gaz Carlos Simoes 4796-5816