Project description

The City of Luxembourg is carrying out redevelopment work in its historic Vieille Ville, more specifically on Rue de la Boucherie, Rue Marché-aux-Herbes, Rue du Palais de Justice and Grand-Rue. These works are being done in collaboration with:

  • VDL – Service Voirie (Roads Department): redevelopment of the urban space across the entire city centre.
  • VDL – Service Eaux (Water Department): replacement of water mains. Connection of houses to the new mains.
  • VDL – Service Canalisation (Sewer Department): replacement of the wastewater and rainwater drains, as well as of connections to houses.
  • VDL – Service Éclairage public (Public Lighting Department): replacement of public lighting.
  • VDL – Service TIC (ICT Department): installation of a fibre-optic network with Hotcity posts.
  • Creos Luxembourg SA Électricité: replacement of the electrical cables in the pavements and the connections to houses.
  • Creos Luxembourg SA Gaz: replacement of gas mains. Connection of houses to the new mains.
  • Post Luxembourg: replacement and enhancement of networks in the pavement and of the connections to houses.

Works schedule

Commencement of work: autumn 2018

Planned duration: 24 months

Planned completion: autumn 2020

Traffic information

What is the current traffic situation?

For vehicular traffic:

The affected streets will be closed off to traffic, one by one, as the project progresses. Rue du Curé, Rue de la Boucherie and Rue Marché-aux-Herbes are completely closed to traffic.

Vehicular access to private properties will be maintained as long as physically possible. Pedestrian access and access for emergency services will be guaranteed throughout the duration of the works.

For businesses and deliveries:

The City of Luxembourg will try to ensure access for deliveries to local businesses throughout the duration of the works.

For public transport users:

No changes.

As construction progresses, the traffic constrictions will change.

Progress to date

Project update:

The works have been under way since November 2018.

How long will the work take?

Planned completion: autumn 2020

What work has already been completed?

The infrastructure work on Rue du Curé and Rue de la Boucherie has been has been completed. What remains to be done is the laying of natural stone paving.

What remains to be done?

The contractor is currently working on the sewer network on the section of Rue Marché-aux-Herbes between Grand-Rue and Rue de la Boucherie.

Your home utility connections

  • As part of the construction project, City representatives and private contractors will visit residents' homes
  • to assess the condition of their existing connections.
  • If you wish to have your existing connections replaced, please inform the City representatives during this on-site inspection.

If you experience any problems with your gas, water or communications networks, please call the numbers below, which are available 24/7:

  • Service Eaux – Tel: 4796-2883
  • Creos Électricité – Tel: 8002-9900
  • Creos Gaz – Tel: 8007-3001
  • Post Luxembourg – Tel: 8002-8004
  • Eltrona – Tel: 499 466 888

Stay informed

To make life easier for residents while these works are being carried out, the City of Luxembourg has implemented a series of measures, including the option to participate in meetings regarding the progress of the work. Residents affected by the works may participate in these meetings to obtain additional information about the project's progress and present any complaints they may have.

Weekly site meetings

Every Tuesday at 14:00

Contacts for this work site

DEPARTMENT CONTACT TELEPHONE

VDL – Service Coordination des chantiers

Serge Courte

4796-3822

VDL - Service Eaux

Carole Kirch

4796-4304

VDL – Service TIC

Michael Da Silva

4796-3380

VDL – Service Circulation

Josh Den Hollander

4796-3344

VDL – Service Éclairage public

Daniel Perrard

4796-4989

VDL – Service Voirie

Bob Bremer

4796-3032

VDL – Service Canalisation

Gilles Biskup

4796-3302

VDL – Construction mediators

chantiers@vdl.lu

4796-4343

Creos Luxembourg Gaz

Gary Scheid

2624-5821

Creos Luxembourg Electricité

Pitt Mertens

2624-5714

POST Télécommunication

Pitt Mertens

2624-5714


Contact
the department

Contact details

20-22, rue des bains
L-1212 Luxembourg

Opening hours

Monday–Friday

8:30–17:00

Contact details

3, rue du Laboratoire
L1911 Luxembourg

Getting there by bus