Project description

Next phase of the Luxtram road works on Avenue de la Liberté (section between Place de Paris and Place de la Gare). Traffic flows on Avenue de la Gare will be reorganised.

Works schedule

Commencement: end of 2018

Planned completion: early 2021

Traffic information

As of 12 May 2019, traffic flows will be reorganised on Avenue de la Gare.

Cycling route

Creation of a safe, two-way cycling route between the Gare and Ville Haute areas.

Bus route

Buses to Ville Haute deviated via Avenue de la Gare and Rue Jean Origer.

Delivery zones

New delivery zones have been created.

Progress to date

What remains to be done?

Since late 2018, work on the sewers and the installation of water and gas mains, dry utility networks and paving have been under way on Avenue de la Liberté between Place de Metz and Place de Paris. This work will be carried out first on the even-numbered side of the street and then on the odd-numbered side. Preparatory work began in May 2019 at the same time on Avenue de la Liberté between Place de Paris and Place de la Gare. Work on the sewers, water and gas mains, dry utility networks and paving will then begin on the even-numbered side of the street. After completing the work on the even-numbered side of the street, the contractor will do the same on the odd-numbered side.

Stay informed

To make life easier for residents while these works are being carried out, the City of Luxembourg has implemented a series of measures, including the option to participate in site meetings. Residents affected by the works may participate in these meetings to obtain additional information about the project's progress and present any complaints they may have.

Contacts for this work site

Department

Contact

Telephone

VDL – Construction mediators chantiers@vdl.lu 4796-4343


Contact
the department

Contact details

Info-box

20-22, rue des bains
L-1212 Luxembourg

Opening hours

Monday–Friday

8:30–17:00