Project description
Creos Gaz, in cooperation with the City of Luxembourg, is currently improving infrastructure in Bonnevoie. Work will be carried out on the following roads: Rue Marguerite-Séraphine Beving, Rue Xavier de Feller, Rue Jean-Baptiste Gellé, Rue Henri Vannérus, and Rue Pierre Krier. The following departments will be involved in this collaborative effort:
- VDL – Service Voirie (Department of Streets): alteration of crossings to meet the needs of people with reduced mobility (PRM) and upgrading of bus stops.
- VDL – Service Eaux (Water Department): replacement of the principal water mains and replacement of home utility connections.
- VDL – Service Canalisation (Sewer Department): replacement of the wastewater and rainwater drains, and of connections to houses.
- VDL – Service Éclairage public (Public Lighting Department): replacement of public lighting.
- VDL – Service Circulation (Traffic Department): extension and upgrade of the existing network.
- Creos Luxembourg SA Gaz: replacement of gas mains and certain home connections.
- Creos Luxembourg SA Électricité: Replacement of the electrical cables in the pavement as well as certain connections to houses.
Works schedule
Commencement of work: September 2019
Planned completion: end of July 2022
Traffic information
What is the current traffic situation?
For vehicular traffic:
Traffic will return to normal on these streets by the end of February, except for Rue Henri Vanérus. The affected sections will be closed off to traffic as the project progresses. At all times, a 3.5-metre passage will remain open to cars. Vehicular access to private property will be maintained as long as physically possible. Pedestrian access and access for emergency services will be guaranteed throughout the duration of the works.
For businesses and deliveries:
The City of Luxembourg will try to ensure access for deliveries to local businesses throughout the duration of the works.
For public transport users:
Buses are once again calling at the stop on Rue Pierre Krier. This will remain the case until works begin on the pavement.
Progress to date
Project update
The works are being performed from 7:00 to 18:00 by a consortium of two contractors (SOGEROUTE/KUHN).
How long will the work take?
Planned completion: end of July 2022
What work has already been completed?
Work on the utility lines on Rue Marguerite-Séraphine Beving, Rue Xavier de Feller, Rue Jean-Baptiste Gellé and Rue Pierre Krier was completed as planned. The final resurfacing works will be carried out at the end of February/March 2022.
What remains to be done?
On Rue Henri Vannérus, the contractor will install two new drains and two bus stops will be added on Rue Pierre Krier. Final road surfacing will be laid as part of the last phase of the works.
Your home utility connections
- As part of the construction project, City representatives and private contractors will visit residents' homes
- to assess the condition of their existing connections.
- If you wish to have your existing connections replaced, please inform the Luxembourg City representatives during this on-site inspection.
If you have any problems with your gas, water or communications networks, please contact the services below, which are open 24/7:
- Service Eaux – Tel.: 4796-2883
- Creos Électricité – Tel.: 8002-9900
- Creos Gaz – Tel.: 8007-3001
- Post Luxembourg – Tel.: 8002-8004
- Eltrona – Tel.: 499-466-888
Stay informed
To make life easier for residents while these works are being carried out, the City of Luxembourg has implemented a series of measures, including the option to participate in meetings regarding the progress of the work. Residents affected by the works may participate in these meetings to obtain additional information about the project's progress and present any complaints they may have.
Weekly site meetings
Every Monday at 14:30 at the site.
Contacts for this work site
DEPARTMENT |
CONTACT |
PHONE NO. |
Creos Luxembourg Gaz |
Gilles Garganese |
2624-5839 |
VDL – Service Eaux |
Steve Philippi |
4796-4346 |
VDL – Service Circulation |
Charel Hoffmann |
4796-2313 |
VDL – Service Éclairage public |
Karim Ainahi |
4796-3883 |
VDL – Service Voirie |
Joé Welter |
4796-2512 |
VDL – Service Canalisation |
Gilles Biskup |
4796-3302 |
VDL – Construction mediators |
4796-4343 |
|
Creos Luxembourg Electricité |
Claude Almeida |
2624-5783 |
POST Télécommunication |
Bureau Technique (Technical Office) |
4991-5763 |